Note to Instructors: This page is automatically created by the current year's AtAGlanceMaker.xlsm, which is available in the current year folder on Box at Capstone-Master/Capstone Wiki Support Files. Make the changes in AtAGlanceMaker.xlsm so they will be consistent with the Excel Schedule. See Editing At-A-Glance Schedules for more information.
Version | 1 | ||||
Week of | M | T | W | Th | F |
26-Aug | Coach Training [DGL] (3 - 5 pm) | ||||
2-Sep | Labor Day | First Day of Class: Class Mechanics, Principles of Design (IPF1) [BRD] WSC 3220 - 3224 - T-shirts | Team Assignment, Working in Diverse Teams, Team Charter (IPF2) [BDJ] WSC 3220 - 3224 - Picture Day | Design Drivers, Divergence/ Convergence, Prototypes (IPF3) [GPN] pods - WSC 3220 - 3228, 3211 | |
9-Sep | Design Details, Deployment, Stages, Requirements Development (IPF4) [BRD] WSC 3220 - 3228, 3211 | Concept Development and Design Considerations (IPF5) [DGL] WSC 3220 - 3228, 3211 | Engineering Economics and Ethics (IPF6) [GPN] WSC 3228, 3250/52, 3380, 3211 & 204/206 EB | First meeting with sponsor; Sponsor kickoff (8-8:50) Lots of rooms for sponsor meetings | Subsystem Engineering and Test Procedures (IPF7) [BDJ] WSC 3220 - 3228, 3211 EB 204 (David), EB 206 (Paula) |
16-Sep | Weekly Status Update 1 due | Workshop: Project Management & Tools | |||
23-Sep | Weekly Status Update 2 due | Team Leader Training [BRD] | |||
30-Sep | Weekly Status Update 23 due | Requirements Review - NLT | |||
7-Oct | Coach Training [DGL] EB 204/206 | Weekly Status Update 4 due | |||
14-Oct | Weekly Status Update 5 due | Individual Contribution scores due | |||
21-Oct | Weekly Status Update 6 due | October Peer & Coach Evaluations Due | |||
28-Oct | Weekly Status Update 7 due | Preliminary Design Review - NLT | |||
4-Nov | Weekly Status Update 8 due | Team Leader Training [BDJ] | |||
11-Nov | Coach Training [DGL] | Weekly Status Update 9 due | |||
18-Nov | Weekly Status Update 10 due | ||||
25-Nov | Friday Instruction | No Classes- NO weekly status update | Thanksgiving | Thanksgiving | |
2-Dec | Weekly Status Update 11 due | ||||
9-Dec | Critical Design Review (CDR) - NLT | Last Day of Classes/ Peer & Coach review due / Weekly Status Update 12 due | Product Development Exam Review (CB 377) | **Saturday: Dec 14: Final Exam on Learning Suite (2:30 -5:30 PM) | |
16-Dec | Individual Contribution scores due | ||||
Table revision 1 made from AtAGlanceMaker revision 1.8 |